Find Work with the Waterfront Resilience Program

The Waterfront Resilience Program includes 6 unique projects that will ensure the waterfront, and its critical regional and citywide assets, are resilient to hazards - and are increasingly accessible to everyone it serves.

As part of the identified Embarcadero Early Projects, these projects are the best positioned to move into final design and construction as early as 2024, providing opportunities for Local Business Enterprises (LBEs) and Workforce Contractors to develop relationships with primes and public agencies, prepare to submit bids, and to get work.

Take a look at the list of projects below and sign up here to stay in touch with the Waterfront Resilience Program and its opportunities. 

1. Wharf J9 Replacement and Resilient Shoreline Project

Wharf J9

Port PM: Wendy Proctor wendy.proctor@sfport.com

Phase: Alternatives Analysis

Total Cost: To Be Determined 

Duration: To Be Determined 

Complexity: Moderate

*Cost and duration are initial planning level estimates and will be refined during Pre-Design.

Scope of Work May Include: Surveying, site investigation and existing conditions assessment, detail design, demolitions, pile installation, reclamation, soil improvements, utilities relocation and replacement, buildings relocation, paving and new berthing facilities. 

Learn More

2. Pier 15 Bulkhead Wall and Wharf Substructure Earthquake Safety Retrofit Project
Pier 15

Port PM: Matt Bell matthew.n.bell@sfport.com

Phase: Alternatives Analysis

Total Cost: To Be Determined 

Duration: To Be Determined 

Complexity: Low

*Cost and duration are initial planning level estimates and will be refined during Pre-Design.

Scope of Work May Include: Surveying, site investigation and existing conditions assessment, detail design, retrofit of structural elements, utilities relocation and replacement, piles installation. 

Learn More

3. Pier 9 Bulkhead Wall and Wharf Substructure Earthquake Safety Retrofit Project
Pier 9

Port PM: Matt Bell matthew.n.bell@sfport.com

Phase: Alternatives Analysis

Total Cost: To Be Determined 

Duration: To Be Determined 

Complexity: Low

*Cost and duration are initial planning level estimates and will be refined during Pre-Design.

Scope of Work May Include: Surveying, site investigation and existing conditions assessment, detail design, retrofit of structural elements, utilities relocation and replacement, piles installation. 

Learn More

4. Ferry Building Seawall and Substructure Earthquake Reliability Project
Ferry Building

Port PM: Steven Reel steven.reel@sfport.com

Phase: Alternatives Analysis

Total Cost: To Be Determined 

Duration: To Be Determined 

Complexity: High

*Cost and duration are initial planning level estimates and will be refined during Pre-Design.

Scope of Work May Include: Surveying, site investigation and existing conditions assessment, detail design, demolitions, pile installation, reclamation, soil improvements, utilities relocation and replacement, buildings relocation, paving and new berthing facilities.  

Learn More

5. Downtown Coastal Resilience Project
Pier 5 - 22.5

Port PM: Wendy Proctor wendy.proctor@sfport.com

Phase: Alternatives Analysis

Total Cost: To Be Determined 

Duration: To Be Determined 

Complexity: Moderate

*Cost and duration are initial planning level estimates and will be refined during Pre-Design.

Scope of Work May Include: Surveying, site investigation and existing conditions assessment, detail design, demolitions, utilities relocation and replacement, floodproofing works, deployable flood protection systems, paving.

Learn More

6. Pier 24-1/2 to Pier 28-1/2 Bulkhead Wall and Wharf Substructure Earthquake Safety Retrofit Project
Pier 24 - 28.5

Port PM: Matthew Bell matthew.n.bell@sfport.com

Phase: Alternatives Analysis

Total Cost: To Be Determined 

Duration: To Be Determined 

Complexity: Low

*Cost and duration are initial planning level estimates and will be refined during Pre-Design.

Scope of Work May Include: Surveying, site investigation and existing conditions assessment, detail design, retrofit of structural elements, utilities relocation and replacement, piles installation, floodproofing works, paving. 

Learn More

7. Pier 35 1/2 Emergency Firefighting Water System (EFWS) Fireboat Manifold Earthquake Reliability Project
Pier 35 1/2 EFWS EEP

Port PM: Matthew Bell matthew.n.bell@sfport.com

Phase: Needs Assessment

Total Cost: To Be Determined 

Duration: To Be Determined 

Complexity: Low

 

Scope of Work May Include: Surveying, site investigation and existing conditions assessment, detail design, demolitions, marine construction and dredging, soil improvements, new berthing facilities. 

Learn More

Stay Connected

Stay up to date with Port of San Francisco and Waterfront Resilience Program opportunities, bid timelines and more.

Sign up here to receive updates